Permit-to-Work and Lockout/Tagout (LOTO)

How permits control high-risk work, and how isolation with locks and tags prevents unexpected release of hazardous energy.

Intermediate35 min studyPublished 2026-09-12Last reviewed 2026-10-01

Why it matters

Many serious injuries happen when equipment starts up or energy is released during maintenance. PTW and LOTO are the systems designed to stop that.

Who it's for: Maintenance staff, supervisors, permit issuers and contractors.

Learning objectives — by the end you can:

  • Describe the roles in a permit system: issuer, receiver, authoriser.
  • List the main LOTO steps from preparation to restoration.
  • Explain why 'try' / verification of zero energy is essential.

Key terms

Permit-to-work (PTW)
A formal written system authorising specific high-risk work under defined controls.
Hazardous energy
Electrical, mechanical, hydraulic, pneumatic, chemical, thermal or stored energy.
Isolation
Separating equipment from all energy sources.
Personal lock
A lock applied by each worker; only they hold the key.

Lesson notes

LOTO sequence (general)

  1. 1Prepare: identify all energy sources from drawings and site knowledge.
  2. 2Notify affected people.
  3. 3Shut down using normal stop.
  4. 4Isolate every energy source.
  5. 5Apply personal locks and tags.
  6. 6Release or restrain stored energy (bleed, block, discharge).
  7. 7Verify zero energy — try to start, test for voltage with a proven tester.
  8. 8Do the work.
  9. 9Restore: clear tools and people, remove locks in the agreed order, notify.

PTW essentials

A permit names the work, location, hazards, isolations, precautions, gas tests if needed, the people involved and the time period. It is handed over at shift change and closed formally. A permit is only as good as the site walk-down behind it.

Limitation

This page is awareness-level. Isolation of electrical or process systems must only be performed by authorised, competent people under your site's procedures.

Video lesson

Video to be added

A verified video from an official or reputable channel has not yet been selected for this topic. The text lesson above covers the full content.

Search YouTube for related videos

Practical story: The conveyor that started itself

Fictional teaching example

Situation. A technician cleared a jam on a conveyor after pressing the stop button.

Known facts

  • No lock was applied.
  • An upstream sensor restarted the conveyor automatically.
  • The technician's glove was caught; minor injury.

Decisions

  • Site introduced personal locks and a 'try' step.
  • Automatic restart circuits added to isolation lists.

Outcome. Near-miss reports on the line rose (good reporting) while injuries fell.

Lessons

  • A stop button is not isolation.
  • Automated systems can restart.
  • Always verify zero energy.

Worked example

Worked example: isolation list for a pump

EnergyIsolation pointMethodVerified by
ElectricalMCC panel breaker P-12Breaker off, personal lockVoltage test at motor terminal
Process fluidSuction & discharge valvesClosed, chained and lockedDrain valve opened, no flow
Stored pressureCasingBleed valve openedGauge reads zero

Practice exercise

List every energy source you would expect on an office paper shredder and how you would isolate it before clearing a jam.

Quiz

Question 1

Q1 · Multiple choice

Which step confirms isolation actually worked?

Question 2

Q2 · True / false

True or false: pressing the emergency stop counts as safe isolation for maintenance.

Question 3

Q3 · Scenario

At shift change, work under a permit is unfinished. What should happen?

Sign in to save quiz results.

References

Verify current editions and applicability. Standards are copyrighted; consult licensed copies for exact requirements.